Tal Tamer power station returns to work after repairing damage caused by Turkish occupation’s shells

Hasaka, SANA- Electricity was restored to residential neighborhoods and villages in Hasaka countryside after repairing the damage the 66kv high-voltage power line feeding Tal Tamer power transmission station which went of service due to Turkish aggression.

Director of Hasaka Electricity Company, Eng. Anwar Aukla, said in statement to SANA reporter, that the station returned to work , noting that the Turkish occupation attack has caused damage to the high-voltage power line for the second time within a week.

On Friday, Turkish occupation and their terrorist mercenaries targeted with artillery shells Umm al-Kif, Tal Juma’a,Tal Karbet in Tal Tamer town in Hasaka northwestern countryside.

Shaza Qreima

Check Also

Lavrov: guarantor states of Astana format agreed to stop military operations in Syria

Doha, SANA- Russian Foreign Minister Sergey Lavrov said that the guarantor states of the Astana …